Office Move Checklist: A Timeline From Lease to Day One

A good office move checklist does two jobs: it puts every task in date order, and it gives each task one owner. Start with the lease and the building’s move rules, then budget, IT, people, packing and move day, and finish with the old space. Below is the full list, built around a timeline you can adapt to a 10-person studio or a 100-desk floor.

Caseys Movers
Make Your Office Move Easier
Caseys Movers provides tailored office relocations with one truck and one crew, for personalized attention and careful management throughout the move.

Explore moving services

TL;DR

  • Start 3 to 6 months out for most offices. Read both leases first, because notice periods and restoration duties set your real deadlines.
  • Name one project owner and one IT owner. A move with shared responsibility is a move with missed tasks.
  • Ask your mover about the building’s rules and certificate of insurance (COI) in week one. Buildings often refuse crews without one.
  • Freeze IT changes during move week and tell employees the why, when and how early.
  • Plan the old space as a second project: cleaning, repairs and furniture disposal.

Table of Contents

Why an office move is two projects, not one

Most checklists read as if you are only building something new. In practice, you run two projects at once: setting up the new space and properly exiting the old one. Planning guidance from a project-plan template for relocations describes restoring the old space to its contractual condition as the place where relocation budgets most often break. Treat that as a warning, then read your lease before you do anything else.

The other half of the job is people. Advice on business relocations keeps returning to the same point: explain the why, when and how of the move early, including what changes about commutes, parking and desk layouts. Morale is easier to protect than to repair.

The timeline at a glance

Use this as a skeleton. Shrink it for a small team, stretch it for a larger one.

WhenFocusKey outputs
4 to 6 months outLease, budget, locationSigned lease for new space, notice sent on old one, budget approved
3 months outTeam and vendorsProject owner, IT owner, mover quotes, floor plan
8 to 12 weeks outInventory and IT planAsset list, decommission plan, internet ordered
4 to 6 weeks outBuilding paperwork, communicationCOI filed, elevator booked, staff briefed, address changes started
2 weeks outPacking startsSupplies delivered, labeling system live, purge complete
Move weekExecutionCrew scheduled, IT freeze, final walkthrough of old space
After the moveSettling inPunch list, address updates finished, old space handed back

4 to 6 months out: lease, budget and the old space

Read both leases

Pull the lease for your current space and check three things: the end date, the notice period for leaving, and what the lease says about the condition you must leave the space in. Many leases require repairs, removal of added walls or cabling, and professional cleaning. Write each obligation down with a cost next to it.

Then read the new lease for move-in terms: when you get keys, whether there is a free-rent or build-out period, and what the building requires of outside contractors.

Build a budget with the unglamorous lines in it

A realistic budget goes beyond the moving crew. Include:

  • Moving and packing labor
  • Storage if the dates do not line up
  • Restoration and cleaning of the old space
  • Cabling, internet installation and any new hardware
  • New signage, keys, access cards and printed stationery
  • Furniture purchases or disposal
  • Overlap rent, if you hold both spaces for a few weeks
  • A contingency line, so that one surprise does not become a crisis

A move rarely fits a single invoice, so it helps to keep the budget in one shared document that the project owner updates weekly.

Decide what is coming with you

Moving a desk costs the same whether it is a good desk or a bad one. Walk the floor and sort every item into keep, sell or donate, and dispose. Old filing cabinets, broken chairs and unused monitors are the usual suspects. If you plan to retire a lot of furniture, read our note on sustainable office furniture decommissioning before you call a dumpster.

3 months out: owners, vendors and the floor plan

Assign the roles

Name one project owner who tracks the timeline, vendor contacts, account numbers, floor plans and cutover dates. IT guidance for small businesses suggests keeping that information in one shared document with a single owner, because details scattered across inboxes are what go missing at 6 p.m. on a Friday.

Add a point person for each department, someone who can answer “where does this go?” on move day without calling you.

Get mover quotes the right way

Ask every mover the same questions, so the quotes compare:

  1. Are you licensed and insured, and can you provide a COI naming our building?
  2. Will you do an in-person or video walkthrough of both spaces?
  3. What is included: packing, disassembly and reassembly of workstations, floor protection, debris removal?
  4. How many crew members and trucks will be on site, and will the same crew do both loading and unloading?
  5. What happens if the freight elevator slot is shorter than planned?
  6. How is the job charged: flat, hourly or by scope?

The one-crew question matters more than it looks. When a crew that loaded your files is the same crew that unloads them, labeling errors get caught on the spot. It is also how we work: each job gets its own truck and its own crew from start to finish.

Draw the new floor plan

Number every workstation, meeting room and storage area on the plan. Those numbers go on labels at the old space and signs at the new one, so a crew member who has never seen your office can place a monitor correctly. Our short piece on five things to consider in an office move covers the planning decisions that come before the plan itself.

8 to 12 weeks out: inventory and IT

Inventory what you own

Build a list of furniture, equipment, servers, phones, printers, safes and specialty items. Flag anything fragile, oversized or regulated, such as medical or lab equipment, art, and large format printers. Those items often need specific handling and sometimes a separate crew or crate.

Plan the technology move

Internet service is the item with the longest lead time, so order it first and ask for a confirmed install date in writing. A phased approach usually beats a single big-bang cutover: infrastructure guidance recommends installing cabling, switches and firewall in the first weeks, then commissioning the connection and testing.

Then apply the stable-state rule. IT specialists advise that you avoid new network configurations, permission changes or software rollouts during move week, so that when something does not work after reconnecting, you know it is the move and not a change you made.

IT checklist:

  • Back up everything, and test a restore before the move
  • Photograph the back of every workstation and the server rack before unplugging
  • Label cables at both ends and color-code them by room
  • Decide which equipment your team carries themselves (laptops, hard drives) and which the crew moves
  • Confirm phone system porting dates, if numbers are changing carriers
  • Schedule a technician on site for the first morning at the new space

Check your records

Businesses registered in Oregon list a principal place of business with the state, and the Secretary of State’s annual report and renewal page shows where that address and the mailing address for notices are entered. Confirm how and when to update yours, and do the same with your bank, insurer, payroll provider and licensing bodies.

4 to 6 weeks out: the building’s rules

This is the section most generic checklists skip, and it is the one that causes the worst move-day delays.

Certificate of insurance

Many managed office buildings will not let a moving crew through the door without a COI on file. The process is rigid: the certificate typically names the property owner and the management company as additional insureds, and it can take a day or two to issue, according to a Portland-area tenant handbook for a downtown office property. Ask both buildings for their exact wording, send it to your mover, and file the COI early. Our apartment moving checklist covers the same step for residential buildings, and the logic is identical.

Freight elevators, floor protection and hours

Commercial buildings in Portland commonly set conditions on how a move happens. The same handbook describes protecting common areas with materials such as 4’ x 8’ sheets of Masonite, reserving freight elevators, and sticking to off-hours schedules, often before 7 a.m. or after 5 p.m. on weekdays, or any time on weekends. It also warns that failing to comply can mean being denied access or paying for damage. Those are one property’s rules, so ask your own building manager for theirs, in writing, for both the old and new address.

Building checklist:

  • Request the building’s move-in and move-out rules for both addresses
  • Reserve the freight elevator for loading and unloading, with buffer time
  • File the COI and get written confirmation of approval
  • Confirm loading dock or street parking, and whether a permit is needed
  • Ask who supplies floor and wall protection, and who removes it
  • Collect keys, access cards and parking passes for the crew

Brief your team

Send a first announcement as soon as the move is certain, and a detailed one at four to six weeks. Include the address, the date, commute and parking changes, what each person packs themselves and the deadline for doing it. Include a seating chart or at least the neighborhood each team will sit in.

2 weeks out: packing and labeling

Purge first, pack second

Shred or recycle what you are not required to keep, using your own retention policy as the guide. Fewer boxes means a shorter move and a cheaper one.

A labeling system that works

Give each box three pieces of information: destination room number, department or owner, and a box count (“3 of 12”). Color-coded tape by zone speeds things up further. Tag furniture the same way, and attach the matching number to the spot on the new floor plan.

A few packing rules:

  • Employees pack their own desks, and the mover packs shared areas, kitchens, supply rooms and anything heavy or fragile
  • Keep sensitive files and confidential records in sealed, numbered containers that travel in a tracked sequence
  • Pack a “first day” box for each department: chargers, markers, tape, power strips and basic supplies
  • Disassemble workstations only once, and keep hardware in labeled bags taped to the part they belong to

If you would rather not pull your staff off their work, professional packing services can handle the supply rooms, libraries and storage areas while your team packs only what is personal.

Plan around gaps in dates

If your old lease ends before the new space is ready, or the reverse, you have a gap. Short-term storage covers it. Our short-term storage cost guide explains how to compare a monthly unit with a mover’s vault.

Move week: execution

The day before

  • Confirm crew arrival time, elevator slot and COI one last time
  • Unplug and tag electronics; employees take laptops home
  • Walk the old space with the project owner and photograph its condition
  • Place signs at the new space showing which room is which
  • Make sure someone with authority is reachable at both addresses

Moving day

Assign one person at the old space to release items and one at the new space to direct them. Both carry the floor plan and the inventory list. Check each load off as it arrives, and note any damage the moment it is seen, not three days later.

To hold a high-pressure day together, keep the order of operations simple: IT core and server equipment first, then furniture, then boxes, then the contents of shared areas. Break rooms and reception go last in and first to be set up, because guests and staff will see them first.

Office move day loading and setup sequence

If you need extra hands only for loading, unloading or rearranging, labor-only help can supplement your own crew.

After the move: the first two weeks

Settling in

  • Test every phone line, printer, badge reader and conference room display
  • Walk the space with department leads and keep a punch list with an owner and date for each item
  • Check that nothing is missing against the inventory, and report any claims promptly
  • Confirm internet speed and Wi-Fi coverage in every corner

Finish the address changes

Update your website, Google Business Profile, email signatures, invoices, insurers, bank, tax and licensing records, vendors and subscriptions. Update the mailing address for notices with the state if it has changed, and set up mail forwarding for at least a few months.

Close out the old space

This is the second project. Remove what the lease requires you to remove, schedule professional cleaning, repair what you damaged and do a final walkthrough with the landlord. Return keys and access cards, and request written confirmation that the space is accepted. Furniture you did not bring can be hauled away, donated or recycled; ask about junk removal and hauling when you book the move so it all happens on one schedule.

Our perspective: where office moves go wrong

We have moved offices in and around Portland, and the problems that sink a move are rarely about lifting. They are about information that did not reach the right person at the right time.

Three patterns show up again and again. First, the building’s rules are discovered on the morning of the move rather than a month before. Second, nobody owns the IT plan, so it is everyone’s side job. Third, the old space is forgotten until the last week, when the landlord’s list arrives.

This is why we run each job as one truck with one crew. The people who walk your space during the estimate are the same people who plan the load, and the same ones who set up at the other end. We think open communication and detailed planning matter more than speed, and we would rather ask you ten questions in week four than fix a problem on move day. If something fragile or oversized is in the inventory, tell us early so we can plan the right protection.

— Steven

Let us handle the heavy part

If you want a crew that arrives on time, handles your building’s paperwork and treats your equipment carefully, take a look at our office and commercial moving service. We are fully licensed and insured, and we offer packing, furniture disassembly and reassembly, storage and junk removal alongside the move itself. Our piece on the benefits of hiring professional movers for a commercial move explains what that looks like in practice.

FAQ

How early should you start planning an office move?

For most offices, three to six months before the move date is a sensible starting point, and earlier if you are still searching for space or your lease has a long notice period. Small teams in a ready-to-use space can compress it into six to eight weeks. The tasks that cannot be rushed are the lease notice, internet installation and the building’s COI process.

Who should manage the move?

One named project owner, with a separate IT owner and a point person in each department. A shared responsibility slows down decisions and leaves gaps. The project owner does not need to do every task, only to track each one and to make the final call.

What is a certificate of insurance, and why does my mover need one?

It is a document from the mover’s insurer proving coverage, and many commercial buildings require it before crews can enter. It usually names the building’s owner and property manager as additional insureds. Ask both buildings for their exact requirements as soon as you have a date, since issuing it can take a day or two.

Should employees pack their own desks?

Yes for personal items and desk contents, with a clear deadline and labeled boxes. Let the mover pack shared areas, equipment, heavy items and anything fragile. This keeps costs down without risking the items that are hardest to replace.

What is the most overlooked task in an office move?

The old space. Restoration, cleaning and repairs required by the lease are frequently left to the end, and they are a common source of budget overruns. Read the lease early, list each obligation and schedule the work for the days right after move-out.